PROTECTION BREAKWATER IN SWINOUJSCIE

  • It is a part of large project, the construction of LNG-Terminal in Swinoujscie, together with construction of a new harbour: brakewater, piers for ships, roads, instalaltions etc.

  • The construction of brakewater is protected with piles, geotextile, stones and big concrete blocks called XBLOC.

  • Additional part of breakwater is covered by another type of blocks, the tetrapods, made of reinforced concrete

​

​

The contracted amounts of XBLOCS:
- 1,0 m3 – 10.600 pcs
- 2,5 m3 – 15.800 pcs
- 5,0 m3 – 2.000 pcs

Tetrapods: 1,4 m3 – 3.000 pcs

Project realisation: 2011-2013.